Peikko delivered and installed the steel frame of the expansion of Terminal 2 in Helsinki Airport. The project received two awards at the end of 2021: The Steel Structure of the Year and The Site of the Year.

The expansion of Terminal 2 is the biggest investment project of the airport company Finavia. The expansion area of the terminal is 42,000 m² and it has been planned based on adaptability. With DELTABEAM®, the terminal and its features can be easily modified in the future, if needed.

DELTABEAM® also allows freedom of design. At the airport, there is a diamond shaped structure on the frame, which is made possible with DELTABEAM®

Peikko delivered and installed:

  • 3.9 km DELTABEAM® composite beams
  • 2,400 tons of other steel structures
  • a lot of different connections items

In addition to the steel structures, Peikko also installed 4,500 concrete elements on site. The installation was made by Peikko Finland's subsidiary, Peikko On-Site Services.

Read more down-arrow.png

DELTABEAM® is a safe and flexible solution for the whole building process. 

Jukka Nikkola, Site Manager, SRV

Project facts

Project size:
42 000 m2
Developer:
Finavia Oyj
Construction Company:
SRV
Structural Designer:
Ramboll Finland Oy
Architect:
Arkkitehtitoimisto ALA Oy
Delivery year:
2019 - 2020
Completion year:
2021